DTG Mould Trade Process |
|
|
Quote |
According to sample, drawing and specific requirement. |
|
Discussion |
Mold material, cavity number, price, runner, payment, etc. |
|
S/C Signature |
Approval for all the items |
|
Advance |
Pay 50% by T/T |
|
Product Design Checking |
We check the product design. If some position is not perfect, or can not be done on the mould, we will send customer the report. |
|
Mould Design |
We make mould design on the basis of confirmed product design, and send to customer for confirmation. |
|
Mold Tooling |
We start to make mold after mold design confirmed |
|
Mold Processing |
Send report to customer once each week |
|
Mold Testing |
Send trial samples and try-out report to customer for confirmation |
|
Mold Modification |
According to customer’s feedback |
|
Balance settlement |
50% by T/T after the customer approved the trial sample and mould quality. |
|
Delivery |
Delivery by sea or air. The forwarder can be designated by your side. |